TEMPORARY PROJECT SIGNAGE
SECTION 01 58 13
TEMPORARY PROJECT SIGNAGE
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Project identification sign.
B. Project informational signs.1.02 RELATED REQUIREMENTS
A. Contract Documents - Uniform General Conditions and Supplemental General Conditions for the State of Texas; and Special Conditions: Requirements for this Section, in addition to requirements herein.
1.03 REFERENCE STANDARDS
A. FHWA (SHS) - Standard Highway Signs; Federal Highway Administration, U.S. Department of Transportation; 2004.
1.04 QUALITY ASSURANCE
A. Design sign and structure to withstand 90 miles/hr wind velocity.
B. Sign Manufacturer to have experience in manufacturing signage with references on similar projects.
C. Finishes, Vinyl: Adequate to withstand weathering, fading, and chipping for duration of construction.1.05 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements for submittal procedures.
B. Shop Drawing: Show content, layout, lettering, color, foundation, structure, sizes and grades of members.
PART 2 PRODUCTS
2.02 MANUFACTURERS
A. Signs:
1. Your Sign Company, LLC. (YSC)
2. Substitutions: See Section 01 60 002.02 SIGN MATERIALS
A. Structure and Framing: New, wood, structurally adequate.
B. Sign Surfaces: Exterior grade plywood with medium density overlay, minimum 3/4 inch thick, standard large sizes to minimize joints.
C. Rough Hardware: Galvanized.
D. Vinyl: Exterior quality; sign background of color as selected.
E. Lettering: Vinyl or digitally printed, colors as selected.2.02 PROJECT IDENTIFICATION SIGN
A. One vinyl graphic sign, 64 sq ft area, bottom 4 feet above ground.
B. Graphic Design, Colors, Style of Lettering: Designated by Architect.2.03 PROJECT INFORMATIONAL SIGNS
A. Vinyl informational signs of same colors and lettering as Project Identification sign, or standard products; size lettering to provide legibility at 100 foot distance.
B. Provide at field office, and directional signs to direct traffic into and within site. Relocate as Work progress requires.
C. Provide municipal traffic agency directional traffic signs to and within site.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install project identification sign within 14 days after date fixed by Notice to Proceed.
B. Erect at designated location.
C. Erect supports and framing on secure foundation, rigidly braced and framed to resist wind loadings.
D. Install sign surface plumb and level. Anchor securely.
E. Exposed surfaces of sign, supports, and framing to be treated lumber.3.02 MAINTENANCE
A. Maintain signs and supports clean, repair deterioration and damage.
3.03 REMOVAL
A. Remove signs, framing, supports, and foundations at completion of Project and restore the area.
END OF SECTION